Today the mayor of the city M.Mukayev inspected the work of major repairs of highways

Today the mayor of the city M.Mukayev inspected the work of major repairs of highways ul.Neyusypova from ul.Sarayshyk to ul.Sdykov. Contractor LLP "DSK Priority". Preparation of the base for the a / b coating, at present 70% of the repair work is performed. ul.T.Masin from ul.Kurmangazy to the Ecological and Biological Center of Uralsk. Contractor LLP "DSK Priority". Work is underway to install sidewalks and prepare for an a / b coating. At present, 65% of the repair work has been completed. Gagarin street / S. Datov street with the device of right turns.
 

Contractor LLP "KZ Projeсt Constractions". Work is under way on the preparation of crushed stone for the a / b coating, putty and plastering of the walls of the underground passage. At present, 85% of repair work has been completed. Akim of the city gave an order to control the quality of the works carried out, as well as to complete the construction work as soon as possible.


26.08.2018 10:47